I began work on this project in the summer of 2018. The first series of slides show the concept drawings  I made in 3D Studio. The idea was to pull together sections of my home that happened as separate projects over many years.  The net is a continuous flow in the basement shop areas that are half below grade and open out under the deck.  Above, an enlarged kitchen that takes full advantage of the view is more appropriate to the overall scale of the house. The living room extends as well to continue the line of deck facing windows.  As of this writing, March 2022, all of the structural work is complete. Remaining to be done are deck railings, drawers and doors for the kitchen, interior plastering and flooring, among other things.  You can follow this page by choosing one of the subscribe options above.
Conceptuals
![Drone view of existing
The center section was the original gambrel with attached garage. I bumped out the garage to create a studio and added the wing on the right later as a master bedroom.](https://jnudb3.p3cdn1.secureserver.net/wp-content/uploads/cache/remote/jnudb3-p3cdn1-secureserver-net/52793012.jpg)
Excavate
![The existing bumpout for the kitchen would remain, establishing the new line of the walls and windows.](https://jnudb3.p3cdn1.secureserver.net/wp-content/uploads/cache/remote/jnudb3-p3cdn1-secureserver-net/2277238633.jpg)
![The plan for supporting the 20' steel beam that would replace the block wall. I cut down the size of the beam by supporting it in the middle., But it needed additional support under the footings. We dug out a cavity, set up a form and shoveled in a nice cement mushroom. The beams hoding up the kitchen bumpout would be replaced by angled supports from the base of the wall](https://jnudb3.p3cdn1.secureserver.net/wp-content/uploads/cache/remote/jnudb3-p3cdn1-secureserver-net/1398206990.jpg)
Kitchen
![Had to jack up the center of the house to get a modestly level floor...replaced the old jack posts with lalley's. Raised that center beam about an inch and a half.](https://jnudb3.p3cdn1.secureserver.net/wp-content/uploads/cache/remote/jnudb3-p3cdn1-secureserver-net/2922409189.jpg)